OVERVIEW
Voltarix Group Inc. (VGI) is planning a 25 megawatt (MW) solar power project on a privately owned greenfield site near the intersection of Township Road 494 and Range Road 271. The proposed Creekside Solar Project (the Project) is approximately one kilometre South of the Town of Calmar, Alberta.
As Alberta phases out coal-fired power plants, the Creekside Solar Project will contribute meaningful renewable energy to meet electricity demand on the local distribution grid. The Project will generate roughly 28,000 megawatt hours of energy, offsetting approximately 4,500 homes and working towards Alberta’s goal of sourcing 30% of the province’s electricity from renewable sources by 2030.
Virtual Open House
Complete
Community Engagement
10060 Jasper Ave, Tower 1
Suite 20205
Edmonton, AB T5J 3R8
OVERVIEW
Voltarix Group Inc. (VGI) is planning a 24 megawatt (MW) solar power project on a privately owned greenfield site near the intersection of Township Road 494 and Range Road 271. The proposed Creekside Solar Project (the Project) is approximately one kilometre South of the Town of Calmar, Alberta.
As Alberta phases out coal-fired power plants, the Creekside Solar Project will contribute meaningful renewable energy to meet electricity demand on the local distribution grid. The Project will generate roughly 28,000 megawatt hours of energy, offsetting approximately 4,500 homes and working towards Alberta’s goal of sourcing 30% of the province’s electricity from renewable sources by 2030.
Virtual Open House
Complete
Community Engagement
10060 Jasper Ave, Tower 1
Suite 20205
Edmonton, AB T5J 3R8
OVERVIEW
Voltarix Group Inc. (VGI) is planning a 24 megawatt (MW) solar power project on a privately owned greenfield site near the intersection of Township Road 494 and Range Road 271. The proposed Creekside Solar Project (the Project) is approximately one kilometre South of the Town of Calmar, Alberta.
As Alberta phases out coal-fired power plants, the Creekside Solar Project will contribute meaningful renewable energy to meet electricity demand on the local distribution grid. The Project will generate roughly 28,000 megawatt hours of energy, offsetting approximately 4,500 homes and working towards Alberta’s goal of sourcing 30% of the province’s electricity from renewable sources by 2030.
Virtual Open House
Complete
Community Engagement
10060 Jasper Ave, Tower 1
Suite 20205
Edmonton, AB T5J 3R8
OVERVIEW
Voltarix Group Inc. (VGI) is planning a 24 megawatt (MW) solar power project on a privately owned greenfield site near the intersection of Township Road 494 and Range Road 271. The proposed Creekside Solar Project (the Project) is approximately one kilometre South of the Town of Calmar, Alberta.
As Alberta phases out coal-fired power plants, the Creekside Solar Project will contribute meaningful renewable energy to meet electricity demand on the local distribution grid. The Project will generate roughly 28,000 megawatt hours of energy, offsetting approximately 4,500 homes and working towards Alberta’s goal of sourcing 30% of the province’s electricity from renewable sources by 2030.
Community Engagement
10060 Jasper Ave, Tower 1
Suite 20205
Edmonton, AB T5J 3R8
Virtual Open House
Complete
OVERVIEW
PROPOSED PROJECT
Voltarix Group Inc. (VGI) is planning a 24 megawatt (MW) solar power project on a privately owned greenfield site near the intersection of Township Road 494 and Range Road 271. The proposed Creekside Solar Project (the Project) is approximately one kilometre South of the Town of Calmar, Alberta.
As Alberta phases out coal-fired power plants, the Creekside Solar Project will contribute meaningful renewable energy to meet electricity demand on the local distribution grid. The Project will generate roughly 28,000 megawatt hours of energy, offsetting approximately 4,500 homes and working towards Alberta’s goal of sourcing 30% of the province’s electricity from renewable sources by 2030.
Community Engagement
10060 Jasper Ave, Tower 1
Suite 20205
Edmonton, AB T5J 3R8
Virtual Open House
Complete
Creekside Solar is a proposed utility scale ground mounted solar photovoltaic (PV) development covering 150 acres of land.
The Project will include approximately 41,000 angled solar modules installed on steel pile foundations and fixed steel racking to a height of 8ft. The entire property will be secured by permanent perimeter chain-link fencing.
VGI will use four inverters to change energy collected by the solar modules from direct current to alternating current in order to transmit it to Fortis Alberta’s existing distribution power facilities.
Voltarix Group is committed to working with independent third party subject matter experts to identify and mitigate the potential impacts of the Creekside Solar project.
-
Adequate setbacks and mitigation measures will be put in place to protect Conjuring Creek.
-
General and seasonal vegetation, wetland and wildlife surveys are currently being conducted to determine potential environmental effects of the project.
-
The historical resource potential will be assessed by the Province of Alberta.
-
A noise impact assessment will be performed in compliance with AUC Rule 012 for Noise Control. Solar energy is general viewed as a very low source of noise impact electricity generator.
-
Solar modules are commonly mistaken to create glare; however, light is absorbed by the module instead of reflected. A glint and glare analysis will be complete to ensure no impacts.
We will continually add our findings to the project website and are committed to share any and all identified risks with the public to ensure all concerns are addressed. All potential impacts will be considered during the design process and impact management plans will be put in place for construction and long term operations.
2021
The first half of 2021 will be spent undergoing consultation and notification with stakeholders within 800m of the Project as well as addressing concerns from the greater Leduc County community. Field studies and solar array design will be performed concurrently.
2022
Prior to 2022, VGI will complete professional third-party studies to evaluate potential impacts as described within the Impact Management section of this information package. All findings will be shared through the project website an included as part of our Alberta Utility Commission (AUC) application for regulatory approval.
2023
Upon Municipal, Provincial, and electrical regulatory approvals VGI plans to construct the facilities beginning spring of 2023, pending seasonal conditions at time of approval. The Creekside Solar project will be commercially operating by Q3 2023.
* Timelines are dependent on many factors and may be extended or accelerated as deemed necessary.
- Why have you chosen this site?
The site was selected for its flat profile and proximity to Fortis Alberta’s Buford substation which distributes electricity across approximately 70,000 hectares of rural Alberta. By producing solar energy in this location, we can help reduce the area’s reliance on carbon emitting electrical generation.
- Is there risk of contamination to the land or air?
No. Solar modules do not leach chemicals and there will be no underground hazardous materials, nor will our project emit dangerous or heat capturing fumes. Voltarix is committed to protect the environment and the communities we build in.
- What will be done to prevent the potential for weeds to contaminate adjacent farmland?
VGI will manage weeds through mechanical means and with selective herbicides, as necessary. If required, we will revegetate the site in consultation with local farmers using a seed mix that will not impact nearby agricultural activities. We will remove any noxious weeds found on the site or will control them without delay, as required by the County.
Creekside Solar is a proposed utility scale ground mounted solar photovoltaic (PV) development covering 150 acres of land.
The Project will include approximately 41,000 angled solar modules installed on steel pile foundations and fixed steel racking to a height of 8ft. The entire property will be secured by permanent perimeter chain-link fencing.
VGI will use four inverters to change energy collected by the solar modules from direct current to alternating current in order to transmit it to Fortis Alberta’s existing distribution power facilities.
Voltarix Group is committed to working with independent third party subject matter experts to identify and mitigate the potential impacts of the Creekside Solar project.
-
Adequate setbacks and mitigation measures will be put in place to protect Conjuring Creek.
-
General and seasonal vegetation, wetland and wildlife surveys are currently being conducted to determine potential environmental effects of the project.
-
The historical resource potential will be assessed by the Province of Alberta.
-
A noise impact assessment will be performed in compliance with AUC Rule 012 for Noise Control. Solar energy is general viewed as a very low source of noise impact electricity generator.
-
Solar modules are commonly mistaken to create glare; however, light is absorbed by the module instead of reflected. A glint and glare analysis will be complete to ensure no impacts.
We will continually add our findings to the project website and are committed to share any and all identified risks with the public to ensure all concerns are addressed. All potential impacts will be considered during the design process and impact management plans will be put in place for construction and long term operations.
2021
The first half of 2021 will be spent undergoing consultation and notification with stakeholders within 800m of the Project as well as addressing concerns from the greater Leduc County community. Field studies and solar array design will be performed concurrently.
2022
Prior to 2022, VGI will complete professional third-party studies to evaluate potential impacts as described within the Impact Management section of this information package. All findings will be shared through the project website an included as part of our Alberta Utility Commission (AUC) application for regulatory approval.
2023
Upon Municipal, Provincial, and electrical regulatory approvals VGI plans to construct the facilities beginning spring of 2023, pending seasonal conditions at time of approval. The Creekside Solar project will be commercially operating by Q3 2023.
* Timelines are dependent on many factors and may be extended or accelerated as deemed necessary.
- Why have you chosen this site?
The site was selected for its flat profile and proximity to Fortis Alberta’s Buford substation which distributes electricity across approximately 70,000 hectares of rural Alberta. By producing solar energy in this location, we can help reduce the area’s reliance on carbon emitting electrical generation.
- Is there risk of contamination to the land or air?
No. Solar modules do not leach chemicals and there will be no underground hazardous materials, nor will our project emit dangerous or heat capturing fumes. Voltarix is committed to protect the environment and the communities we build in.
- What will be done to prevent the potential for weeds to contaminate adjacent farmland?
VGI will manage weeds through mechanical means and with selective herbicides, as necessary. If required, we will revegetate the site in consultation with local farmers using a seed mix that will not impact nearby agricultural activities. We will remove any noxious weeds found on the site or will control them without delay, as required by the County.
Creekside Solar is a proposed utility scale ground mounted solar photovoltaic (PV) development covering 150 acres of land.
The Project will include approximately 41,000 angled solar modules installed on steel pile foundations and fixed steel racking to a height of 8ft. The entire property will be secured by permanent perimeter chain-link fencing.
VGI will use four inverters to change energy collected by the solar modules from direct current to alternating current in order to transmit it to Fortis Alberta’s existing distribution power facilities.
Voltarix Group is committed to working with independent third party subject matter experts to identify and mitigate the potential impacts of the Creekside Solar project.
-
Adequate setbacks and mitigation measures will be put in place to protect Conjuring Creek.
-
General and seasonal vegetation, wetland and wildlife surveys are currently being conducted to determine potential environmental effects of the project.
-
The historical resource potential will be assessed by the Province of Alberta.
-
A noise impact assessment will be performed in compliance with AUC Rule 012 for Noise Control. Solar energy is general viewed as a very low source of noise impact electricity generator.
-
Solar modules are commonly mistaken to create glare; however, light is absorbed by the module instead of reflected. A glint and glare analysis will be complete to ensure no impacts.
We will continually add our findings to the project website and are committed to share any and all identified risks with the public to ensure all concerns are addressed. All potential impacts will be considered during the design process and impact management plans will be put in place for construction and long term operations.
2021
The first half of 2021 will be spent undergoing consultation and notification with stakeholders within 800m of the Project as well as addressing concerns from the greater Leduc County community. Field studies and solar array design will be performed concurrently.
2022
Prior to 2022, VGI will complete professional third-party studies to evaluate potential impacts as described within the Impact Management section of this information package. All findings will be shared through the project website an included as part of our Alberta Utility Commission (AUC) application for regulatory approval.
2023
Upon Municipal, Provincial, and electrical regulatory approvals VGI plans to construct the facilities beginning spring of 2023, pending seasonal conditions at time of approval. The Creekside Solar project will be commercially operating by Q3 2023.
* Timelines are dependent on many factors and may be extended or accelerated as deemed necessary.
- Why have you chosen this site?
The site was selected for its flat profile and proximity to Fortis Alberta’s Buford substation which distributes electricity across approximately 70,000 hectares of rural Alberta. By producing solar energy in this location, we can help reduce the area’s reliance on carbon emitting electrical generation.
- Is there risk of contamination to the land or air?
No. Solar modules do not leach chemicals and there will be no underground hazardous materials, nor will our project emit dangerous or heat capturing fumes. Voltarix is committed to protect the environment and the communities we build in.
- What will be done to prevent the potential for weeds to contaminate adjacent farmland?
VGI will manage weeds through mechanical means and with selective herbicides, as necessary. If required, we will revegetate the site in consultation with local farmers using a seed mix that will not impact nearby agricultural activities. We will remove any noxious weeds found on the site or will control them without delay, as required by the County.
Creekside Solar is a proposed utility scale ground mounted solar photovoltaic (PV) development covering 150 acres of land.
The Project will include approximately 41,000 angled solar modules installed on steel pile foundations and fixed steel racking to a height of 8ft. The entire property will be secured by permanent perimeter chain-link fencing.
VGI will use four inverters to change energy collected by the solar modules from direct current to alternating current in order to transmit it to Fortis Alberta’s existing distribution power facilities.
Voltarix Group is committed to working with independent third party subject matter experts to identify and mitigate the potential impacts of the Creekside Solar project.
-
Adequate setbacks and mitigation measures will be put in place to protect Conjuring Creek.
-
General and seasonal vegetation, wetland and wildlife surveys are currently being conducted to determine potential environmental effects of the project.
-
The historical resource potential will be assessed by the Province of Alberta.
-
A noise impact assessment will be performed in compliance with AUC Rule 012 for Noise Control. Solar energy is general viewed as a very low source of noise impact electricity generator.
-
Solar modules are commonly mistaken to create glare; however, light is absorbed by the module instead of reflected. A glint and glare analysis will be complete to ensure no impacts.
We will continually add our findings to the project website and are committed to share any and all identified risks with the public to ensure all concerns are addressed. All potential impacts will be considered during the design process and impact management plans will be put in place for construction and long term operations.
2021
The first half of 2021 will be spent undergoing consultation and notification with stakeholders within 800m of the Project as well as addressing concerns from the greater Leduc County community. Field studies and solar array design will be performed concurrently.
2022
Prior to 2022, VGI will complete professional third-party studies to evaluate potential impacts as described within the Impact Management section of this information package. All findings will be shared through the project website an included as part of our Alberta Utility Commission (AUC) application for regulatory approval.
2023
Upon Municipal, Provincial, and electrical regulatory approvals VGI plans to construct the facilities beginning spring of 2023, pending seasonal conditions at time of approval. The Creekside Solar project will be commercially operating by Q3 2023.
* Timelines are dependent on many factors and may be extended or accelerated as deemed necessary.
- Why have you chosen this site?
The site was selected for its flat profile and proximity to Fortis Alberta’s Buford substation which distributes electricity across approximately 70,000 hectares of rural Alberta. By producing solar energy in this location, we can help reduce the area’s reliance on carbon emitting electrical generation.
- Is there risk of contamination to the land or air?
No. Solar modules do not leach chemicals and there will be no underground hazardous materials, nor will our project emit dangerous or heat capturing fumes. Voltarix is committed to protect the environment and the communities we build in.
- What will be done to prevent the potential for weeds to contaminate adjacent farmland?
VGI will manage weeds through mechanical means and with selective herbicides, as necessary. If required, we will revegetate the site in consultation with local farmers using a seed mix that will not impact nearby agricultural activities. We will remove any noxious weeds found on the site or will control them without delay, as required by the County.
Creekside Solar is a proposed utility scale ground mounted solar photovoltaic (PV) development covering 150 acres of land.
The Project will include approximately 41,000 angled solar modules installed on steel pile foundations and fixed steel racking to a height of 8ft. The entire property will be secured by permanent perimeter chain-link fencing.
VGI will use four inverters to change energy collected by the solar modules from direct current to alternating current in order to transmit it to Fortis Alberta’s existing distribution power facilities.
Voltarix Group is committed to working with independent third party subject matter experts to identify and mitigate the potential impacts of the Creekside Solar project.
-
Adequate setbacks and mitigation measures will be put in place to protect Conjuring Creek.
-
General and seasonal vegetation, wetland and wildlife surveys are currently being conducted to determine potential environmental effects of the project.
-
The historical resource potential will be assessed by the Province of Alberta.
-
A noise impact assessment will be performed in compliance with AUC Rule 012 for Noise Control. Solar energy is general viewed as a very low source of noise impact electricity generator.
-
Solar modules are commonly mistaken to create glare; however, light is absorbed by the module instead of reflected. A glint and glare analysis will be complete to ensure no impacts.
We will continually add our findings to the project website and are committed to share any and all identified risks with the public to ensure all concerns are addressed. All potential impacts will be considered during the design process and impact management plans will be put in place for construction and long term operations.
2021
The first half of 2021 will be spent undergoing consultation and notification with stakeholders within 800m of the Project as well as addressing concerns from the greater Leduc County community. Field studies and solar array design will be performed concurrently.
2022
Prior to 2022, VGI will complete professional third-party studies to evaluate potential impacts as described within the Impact Management section of this information package. All findings will be shared through the project website an included as part of our Alberta Utility Commission (AUC) application for regulatory approval.
2023
Upon Municipal, Provincial, and electrical regulatory approvals VGI plans to construct the facilities beginning spring of 2023, pending seasonal conditions at time of approval. The Creekside Solar project will be commercially operating by Q3 2023.
* Timelines are dependent on many factors and may be extended or accelerated as deemed necessary.
- Why have you chosen this site?
The site was selected for its flat profile and proximity to Fortis Alberta’s Buford substation which distributes electricity across approximately 70,000 hectares of rural Alberta. By producing solar energy in this location, we can help reduce the area’s reliance on carbon emitting electrical generation.
- Is there risk of contamination to the land or air?
No. Solar modules do not leach chemicals and there will be no underground hazardous materials, nor will our project emit dangerous or heat capturing fumes. Voltarix is committed to protect the environment and the communities we build in.
- What will be done to prevent the potential for weeds to contaminate adjacent farmland?
VGI will manage weeds through mechanical means and with selective herbicides, as necessary. If required, we will revegetate the site in consultation with local farmers using a seed mix that will not impact nearby agricultural activities. We will remove any noxious weeds found on the site or will control them without delay, as required by the County.
The Alberta Utilities Commission regulates power generation in Alberta. The AUC is an independent, quasi-judicial agency of the Government of Alberta, whose mandate is to ensure the delivery of Alberta’s utility services take place in a manner that is fair, responsible and in the public interest.
Information on how you can participate in the AUC’s independent review program can be found on their website at www.auc.ca. You can also contact the AUC by phone at 310-42820 or email at info@auc.ab.ca.
The Alberta Utilities Commission regulates power generation in Alberta. The AUC is an independent, quasi-judicial agency of the Government of Alberta, whose mandate is to ensure the delivery of Alberta’s utility services take place in a manner that is fair, responsible and in the public interest.
Information on how you can participate in the AUC’s independent review program can be found on their website at www.auc.ca. You can also contact the AUC by phone at 310-42820 or email at info@auc.ab.ca.